CREC School Construction Division Relevant Experience

Connecticut Educational (K-12) Projects:

  • Metacomet and Laurel Elementary Schools - Bloomfield
  • Learning Corridor - Hartford
  • University of Hartford Elementary Magnet School - West Hartford
  • Metropolitan Learning Center - Bloomfield
  • John J. Allison, Jr. Polaris Center - East Hartford • River Street School for Autism - Windsor
  • CREC Soundbridge School - Wethersfield
  • Vernon E. Cleaves Vocational Agricultural Center - Wallingford • Carmen Arace Intermediate/Middle School - Bloomfield
  • Sports and Medical Sciences Academy - Hartford
  • Breakthrough Magnet School - Hartford
  • Great Path Academy - Manchester
  • Greater Hartford Classical Magnet School - Hartford
  • University High School of Science and Engineering - Hartford
  • East Hartford Glastonbury Elementary Magnet School - East Hartford
  • Simpson-Waverly Classical Magnet School - Hartford
  • Derby Middle School - Derby
  • CREC Public Safety Academy - Enfield

CREC Owner's Representative Services Projects:

  • Metropolitan Learning Center
    1551 Blue Hills Avenue, Bloomfield, CT Magnet School for Global Studies Grades 6 - 12 147,000 sq. ft., Project Budget $33 million; Project completed on schedule and $1 million under budget; No litigation, No OSHA or safety issues.
  • University of Hartford Magnet School
    196 Bloomfield Avenue, Hartford, CT Magnet School Multiple Intelligence Pre-K – Grade 5 76,000 sq. ft.; Project Budget $21.5 million; Project completed on schedule with $300,000 budget surplus; No litigation, No OSHA or safety issues.
  • John J. Allison, Jr. Polaris Center
    474 School Street, East Hartford, CT Special Education Facility 40,000 sq. ft.; Project Budget $9.5 million Project completed on schedule; $200,000 surplus; No litigation, No OSHA or safety issues.
  • River Street School
    627 River St., Windsor, CT Special Education Facility 9,000 sq. ft.; Renovate as New Project; Budget $3.4 million; Project completed on schedule and within budget; No litigation, No OSHA or safety issues.
  • Soundbridge School
    Progress Drive, Wethersfield, CT Special Education Facility 16,000 sq. ft.; Addition and Renovation Project budget $7,129,000; in progress and is on schedule; Project commenced July 12, 2007.
  • Vernon E. Cleaves Vocational Agricultural Center at Lyman Hall High School
    Wallingford, CT 72,000 sq. ft. addition; Project budget $27,808,000; Project commenced March, 2007 and is on schedule.
  • Carmen Arace Intermediate and Middle School
    Bloomfield, CT 171,552 sq. ft. renovation; Project budget $28,818,300; Project commenced April, 2008 and is on schedule.
  • Metacomet and Laurel Elementary School (additions and renovations) Bloomfield, CT 102,000 sq. ft. additions and renovations (combined); Project budget $22,406,400 (combined); Project commenced May 2009.
  • Connecticut River Academy Magnet High School
    Goodwin College 103,000 sq. ft. new construction; Project budget $57,300,000; Project commenced April 2008.
  • East Hartford Glastonbury Elementary Magnet School
    Glastonbury, CT 67,350 sq. ft. new construction; Project budget $36,300,000; Project commenced April 2009.
 
 
Operations, Facilities & School Construction (860) 524-4060
PD Cancellation/Delay WEBMAIL Intranet SITEMAP NEWS Directions Disclaimer | Visit us on Facebook
CREC: Capitol Region Education Council
111 Charter Oak Avenue · Hartford, CT 06106
(860) 247-2732